Power house of small hydropower plant Jonouli 1 is ready for installation of technology equipment such as hydro turbines with generators and accessories. 

Delivery and assembly of turbines will be finished by the end of April 2018. Work on installation of  the penstocks is ongoing.  We have finished 1300 m now. All activities are going with according  to time schedule.