Two trucks that imported two Francis-type turbines with accessories from the Czech Republic arrived to the construction of the small hydroelectric power plant Jonouli 1 in Georgia on  April 18th, 2018.

In the coming days, the installation of technological equipment will begin under the supervision of the manufacturer's chief installers. Completion of assembly is expected by mid June 2018. At the same time, building of power house continues.